logo
infrastructure-engineering-and-civil

KCDC – Otaki WWTP LDTA Upgrade

KCDC – Otaki WWTP LDTA Upgrade

Contract Value: $490K
Otaki

Contact our Infrastructure Engineering team today!

Reece Lloyd

Reece Lloyd

Infrastructure
Manager

E: reece.lloyd@maxtarr.co.nz
M: 027 455 5576

 

Mask Group 13

Nick Reid

Contracts
Manager

E: nick.reid@maxtarr.co.nz
M: 027 324 3114

Mask Group 21

Dylan Buckingham

Project
Engineer

Contact our Industrial team today!

Mask Group 9

Max Tarr

Executive Director

E: max.tarr@maxtarr.co.nz
M: 027 495 2468

Mask Group 8

Jonathan Hogg

Industrial Manager

E: Jonathan.hogg@maxtarr.co.nz
M: 027 444 2054

michael

Michael Hoggard

Project Manager

Contact our Commercial team today!

Dean Berendt

Dean Berendt

Commercial Manager

E: dean.b@maxtarr.co.nz
M: 022 639 3644

andrew

Andrew Tokley

Project Manager
Mask Group 18

Tony Boerboom

Fire & Security Supervisor

E: tony.boerboom@maxtarr.co.nz
M: 027 497 5697

Otaki LDTA hero
20210507 124645 1
20210409 160755
20210510 123141
20210308 095933
20210305 132213
20210324 112944
Otaki KcDC irrigationB
Otaki KcDC irrigation A
20210510 125134

The scope of work covered fabrication, supply, installation and commissioning of a new automated irrigation system as part of the LDTA Upgrade.

The work included the following items:

Installation of two (2) new effluent pumps (including associated base connection, guiderails, and lifting chain) to replace existing pumps.

Supply and installation of new Variable Speed Drives (VSDs) to suit the new pumps.

Supply and installation of a new OD315 HDPE PN10 header pipe (approximately 400 m long), and tie-in to the existing pump discharge pipe from the pump house.

Supply and installation of 18 valving arrangements for each lateral, from the header pipe, including isolation valve, pneumatically actuated valve and pressure instruments on each. Each valving arrangement is mounted on a new concrete slab.

Design, supply and installation of complete pneumatic system for valve operation including: compressor, receiver and solenoid bank.

Modifying the instrumentation, switchboard, control panel and SCADA control of the effluent pump station and new pneumatically actuated valves to accommodate the new operating regime.

Demolition of the existing three (3) concrete chambers, which includes the central headrace receiving chamber, and the chambers at each end of the existing header pipe.

Supply and installation of a new discharge flow meter.

View other projects

1 2 3 11