logo
infrastructure-engineering-and-civil

Hastings – Frimley WTP

Hastings – Frimley WTP

Contract Value: $1.2M

Contact our Infrastructure Engineering team today!

Reece Lloyd

Reece Lloyd

Infrastructure
Manager

E: reece.lloyd@maxtarr.co.nz
M: 027 455 5576

 

Mask Group 13

Nick Reid

Contracts
Manager

E: nick.reid@maxtarr.co.nz
M: 027 324 3114

Mask Group 21

Dylan Buckingham

Project
Engineer

Contact our Industrial team today!

Mask Group 9

Max Tarr

Executive Director

E: max.tarr@maxtarr.co.nz
M: 027 495 2468

Mask Group 8

Jonathan Hogg

Industrial Manager

E: Jonathan.hogg@maxtarr.co.nz
M: 027 444 2054

michael

Michael Hoggard

Project Manager

Contact our Commercial team today!

Dean Berendt

Dean Berendt

Commercial Manager

E: dean.b@maxtarr.co.nz
M: 022 639 3644

andrew

Andrew Tokley

Project Manager
Mask Group 18

Tony Boerboom

Fire & Security Supervisor

E: tony.boerboom@maxtarr.co.nz
M: 027 497 5697

20220805 112359 1
20220805 112225 1
20220805 112205
20220805 111914
20220805 111838
20220805 111645
20220805 111412
20220805 111358
20220805 111234 1
20220805 111208
20220805 111156

Max Tarr Infrastructure Engineers were sub-contracted by Drainways to the Hastings District Council for the Mechanical supply & installation of the internal S/S 316 pipework and fittings for the Frimley & Eastbourne Water Treatment Plants, which form the districts largest drinking water network serving Flaxmere, Bridge Pa, Hastings and Havelock North.

The Mechanical scope consists mostly of S/S 500NB & 600NB Sch10 welded pipework assemblies, supported by Galvanized pipe supports separated with a neoprene membrane.

The plant equipment includes 5x KSB 160kW Delivery pumps, 2x 500NB WEDECO Spektron 2000e UV Reactors, 2x 3000L Surge vessels, Sodium Hypo & HFA dosing systems

Custom 500NB Static Mixer, 2x 500NB E&H Flow meters, Multiple AVK Butterfly valves (some with Rotork IQT2000 Actuators), 400NB Bermad Pressure Sustaining Valve

Tilting Disk check valves, couplers, service water, Emergency Shower & Eyewash stations, Retractable hose-reels.

The system was pressure tested & super-chlorinated prior to commissioning.